Section 52 SeilbG: who decides the extent of removal, which landowners have party status and who bears the cost of the measures.

Your personal attorney

Mag. Christopher Angerer, Rechtsanwalt

Your lawyer for ski and alpine accidents

Ski and alpine accidents are complex and emotional. One lawyer you know, from the first question to the courtroom. Strong practical background (former ski instructor, mountain rescuer and dog handler).

In larger cases, the work is handled as a team (lawyer, trainee lawyer, legal assistant). Court hearings and negotiations always remain a matter for the lead lawyer.

13 November 2026, Mag. Christopher Angerer, Rechtsanwalt

If cableway operation ceases entirely and permanently, the provincial governor decides under § 52 of the Austrian Cableways Act 2003 (SeilbG) whether and which parts must be removed and whether further measures are required. Complete removal and restoration to a natural state do not follow automatically, and the operator and affected landowners need to establish the specific scope of the measures.

Landowners whose property the cableway uses hold party status in the removal proceedings alongside the cableway undertaking. Before commissioning removal work or treating land as returned, you should review the existing structures, the authority’s requirements, and the contractual arrangements together. It is particularly important to identify which remaining components affect each plot.

What needs clarification for your closed cableway?

Select the current position. This guidance helps you prepare and does not replace an authority’s decision.

Would you like to discuss closure of the installation? Continue to the enquiry form.

01 Question 1

Which situation applies?

Removal

Possible next steps

01

Clarify permanent abandonment first

Use the existing decisions and the operator’s information to clarify whether operation has ceased entirely and permanently. A temporary interruption alone does not establish that § 52 Abs. 3 SeilbG applies.

02

Prepare the scope of removal and documents

Show components to be removed and those to remain in a plot-specific plan. Where operation ceases entirely and permanently, the provincial governor decides on removal and further necessary measures.

03

Identify the affected plot and your procedural position

Check which components use your land and how the documents address them. Affected landowners have party status under § 52 Abs. 2 SeilbG; additional contractual claims require separate examination.

Distinguish permanent closure from a temporary interruption

§ 52 Abs. 3 SeilbG applies where operation ceases entirely and permanently. A seasonal shutdown or temporary closure alone does not establish permanent abandonment. Record the affected installation and whether the operator intends to resume. Existing closure decisions, operator statements, and installation plans help establish the position. Resuming operation after an authority has suspended it on safety grounds involves a different decision. Renewing an expiring concession also requires separate treatment. Establishing the facts allows you to identify the appropriate procedure and the consequences for the remaining installation.

The provincial governor determines which parts must be removed

If operation ceases entirely and permanently, the provincial governor decides under § 52 Abs. 3 SeilbG whether removal is required, its extent, and any further necessary measures. The governor must consider public interests, particularly public safety. Consequently, the specific proceedings require an assessment of stations, supports, foundations, and other affected components. Neither permanent closure nor a landowner’s request alone creates an unconditional entitlement to complete restoration to a natural state under this provision. Anyone seeking removal of a particular component or proposing that it remain should explain its location, condition, and the resulting safety issues in a comprehensible form.

Affected landowners have a role in the proceedings

§ 52 Abs. 2 SeilbG expressly grants party status alongside the cableway undertaking, in particular to owners of land used by the cableway. The specific use of the land is therefore decisive, and merely owning neighbouring land is insufficient under that wording. Owners should bring together the plot number, evidence of ownership, and the components situated on or otherwise using their land. Specific information about remaining components, access, and safety concerns is more useful for presenting their position than a general demand for the land to be returned. Party status does not confer a general veto over every removal decision, nor does it replace a separate examination of private contractual claims.

The documents must show the planned removal measures

§ 52 Abs. 1 SeilbG requires documents showing the planned removal measures for any removal outside an extension or alteration project. The authority grants permission or orders removal and may prescribe supplementary measures. As preparation, a plan should distinguish components to be removed from those to remain and allocate them to the relevant plots. You should explain access for the works, their sequence and proposed safety measures insofar as relevant to the project. These examples are not an exhaustive statutory list of attachments. The authority assesses removal forming part of an extension or alteration within the building approval procedure, and the construction design must include it.

The undertaking, a successor or the bankruptcy estate bears the removal costs

§ 52 Abs. 3 SeilbG charges the cableway undertaking, any legal successor, or the bankruptcy estate with the costs of removal measures. That rule does not impose these costs on a landowner simply because they own land used by the cableway. Before commissioning work, the operator and landowners should clarify which works the authority’s decision covers and who assumes obligations towards the contractor. The statutory allocation does not promise reimbursement for all personal advice, representation, or additional expenses. In insolvency, you should examine the legal allocation and practical funding or recovery separately, since naming the bankruptcy estate does not guarantee payment in full.

Compare the decision, land-use agreement and completed removal

The authority’s specified extent of removal does not automatically resolve every issue stemming from a land-use agreement. Examine separately whether an agreement imposes additional restoration obligations and identify against whom such obligations might exist. The continued validity of registered land-use rights likewise hinges on the relevant instruments, as § 52 does not universally extinguish these rights. To ensure coordination, prepare a record for each plot that details ordered works, remaining components, unresolved contractual issues, and documented progress. Store the decision, plans, and photographs of the post-work condition together. This practice enables a targeted examination of discrepancies between the agreed return condition and the measures mandated by public law.

FAQ

Questions about permanent cableway closure

Must the entire installation disappear after closure? +
When operation ceases entirely and permanently, the provincial governor decides under § 52 Abs. 3 SeilbG whether and which components must be removed and whether further measures are necessary, yet this provision contains no automatic obligation to restore the entire site to a natural state.
Do I have party status as an affected landowner? +
§ 52 Abs. 2 SeilbG expressly refers to owners of land used by the cableway. These owners should document the affected plots and components to establish their position within the particular removal proceedings.
Who bears the cost of removal measures? +
The cableway undertaking, any legal successor, or the bankruptcy estate bears these costs under § 52 Abs. 3 SeilbG, yet the rule does not generally promise to cover all additional private expenses incurred by a landowner.
Related questions

Examine continued operation and the concession separately

Had an accident?