Overdue cableway inspection: secure the report before the season starts

Austrian cableway inspections: the five-year cycle, delivery of the report, six-month tolerance and limited extensions before the season starts.

Your personal attorney

Mag. Christopher Angerer, Rechtsanwalt

Your lawyer for ski and alpine accidents

Ski and alpine accidents are complex and emotional. One lawyer you know, from the first question to the courtroom. Strong practical background (former ski instructor, mountain rescuer and dog handler).

In larger cases, the work is handled as a team (lawyer, trainee lawyer, legal assistant). Court hearings and negotiations always remain a matter for the lead lawyer.

15 November 2026, Mag. Christopher Angerer, Rechtsanwalt

The cableway operator's receipt of the inspection report determines compliance with the periodic inspection deadline, whereas booking an inspection or obtaining an oral assurance is insufficient. If the inspection remains outstanding before the season starts, management must separately check the due date, the six-month tolerance, and any application for an extension.

Which inspection records are missing before the season starts?

The answers identify the next assessment step. They do not authorise operation.

Would you like to discuss inspection duties or an extension? Continue to the enquiry form.

01 Question 1

What is the current position for your installation?

Next assessment steps

Next assessment steps

01

Establish the starting date and delivery of the report

Check the operating permit, earlier reports and delivery records. The correct starting date is needed to establish the due date and application deadline.

02

Secure the report while protecting the application deadline

Arrange delivery within the permitted period. If an extension is needed, apply no later than four weeks before the six-month period ends. An application is not permission, and outstanding safety defects need separate assessment.

03

Review the authority records and permitted operation immediately

Check whether a timely application was made and an extension granted. Do not base operation on an assumed extension. Any existing suspension and the conditions for lifting it require separate assessment.

04

Suspend operation immediately and clarify permission to resume

For the notified immediate operational danger, § 6 Abs. 3 SeilbÜV 2013 requires immediate suspension even without an authority order. Document removal of the danger and the supporting evidence; resumption requires authority permission.

The cableway operator must arrange the inspection in good time

§ 49 of the Austrian Cableways Act 2003 (SeilbG) obliges the cableway operator to arrange periodic and supplementary inspections at its own expense. An accredited cableway inspection body generally must conduct periodic inspections. For non-public installations, the Cableway Inspection Regulation 2013 (SeilbÜV 2013) allows qualified persons and inspection bodies to alternate following the first inspection. Further special rules govern low-rope drag lifts. Consequently, the choice of inspector must correspond to the legal type of installation.

The five-year cycle runs from the legally relevant starting date

§ 3 Abs. 1 SeilbÜV 2013 mandates periodic inspections at five-year intervals. The cycle generally commences on the date the operating permit was granted. Paragraphs 2 to 4 establish special starting points for older public and non-public installations based on earlier inspections. Consequently, the installation records must establish which starting date applies to your cableway.

You may apply to the authority under § 3 Abs. 5 to change that starting date by giving reasons, provided no inspection deadline is exceeded. A late inspection does not itself shift the cycle, and neither the six-month tolerance nor an extension changes the next periodic inspection deadline.

Inspection, delivery of the report and submission to the authority are separate dates

Under § 3 Abs. 6 SeilbÜV 2013, compliance with the deadline depends on the date the inspection report reaches the cableway operator. The inspection body or qualified person must first communicate the result orally and then provide a report within one week after completing the inspection. When commissioning the inspection, plan for the written report and evidence of its delivery.

The operator must submit a copy to the authority within one week of receipt, accompanied by reports on any supplementary inspections performed since the previous periodic inspection. The operator must retain the report and its attachments for the lifetime of the cableway. Should the operator dispute all or part of the findings, it may provide an explanation of its reasons upon submitting the report; in such a case, § 5 Abs. 4 obliges the authority to issue a formal administrative decision within six weeks.

The six-month tolerance does not change the next due date

§ 3 Abs. 7 SeilbÜV 2013 allows the periodic inspection to take place up to six months before or after the regular due date, yet the subsequent inspection deadline stays the same. This tolerance applies only to the periodic schedule; safety defects and other operational obstacles demand a separate assessment. An unexpired inspection deadline cannot justify an immediate operational danger.

Apply for an extension in time and explain the reasons

If the first six months following the due date prove insufficient, you must submit the extension application no later than four weeks before that period expires. The application must explain why an inspection within the deadline appears impossible. Under § 3 Abs. 8, any extension beyond the initial six months is limited to a maximum of an additional six months. The mere submission of the application does not establish that an extension has been granted.

The authority must suspend operation under § 3 Abs. 7 if no inspection occurs during the first six months and no timely application is made. Paragraph 8 also mandates suspension if an inspection fails to take place within the subsequent six months. Under these provisions, suspension continues until a report confirms the cableway is in proper condition. If the application deadline has already passed, seek an immediate legal review of the records and avoid basing the season opening on an assumed extension.

Supplementary inspections follow their own deadlines

§ 3 Abs. 9 SeilbÜV 2013 refers to Annex 2 for supplementary inspections. The component and its legal classification determine the scope, inspectors, and deadlines. The earlier limit applies where both years and operating hours are specified. For components subject to a conformity assessment procedure, the manufacturer's operating and maintenance instructions determine the scope and required inspectors. The five-year inspection does not automatically cover these obligations.

Annex 2, sections 2.1 and 2.3, allow exceeding their numerical deadlines by up to three months without changing the next deadline, but one cannot generally transfer the six-month tolerance for periodic inspections to them. If a periodic inspection shows that supplementary inspections remain outstanding despite the expiry of their deadlines, § 6 Abs. 2 prohibits cableway operation until those inspections have been performed.

Having a report does not resolve outstanding safety defects

The report must record defects and proposals for their correction. Under § 6 SeilbÜV 2013, time limits for correction may be allowed if no immediate operational danger exists. If such a danger exists, the operator must immediately suspend operation upon receiving written notification from the inspector, even without an authority order, and the operator requires authority permission to resume. Evidence of correction and, where applicable, the final report must remain in the deadline schedule for other identified defects.

Keep alterations, general overhaul and periodic inspection separate

The general overhaul under § 49a SeilbG expressly leaves inspections under § 49 unaffected. A construction or operating permit does not automatically replace the due report either. § 2 Abs. 1 SeilbÜV 2013 allows a narrow substitution only where an authority inspection under § 50 occurs within the deadline and covers the entirety of Annex 1; supplementary inspections remain unaffected. Under § 4 Abs. 2, the following periodic inspection must take into account certain functional tests from alteration proceedings if performed no more than two years earlier. An alteration alone therefore does not replace a complete inspection.

Complete the deadline records before the season starts

Gather the operating permit, previous inspection reports, evidence of delivery, supplementary inspections, and outstanding defects for legal review. Record the relevant starting date, the regular due date, the end of the six-month tolerance, and the application deadline separately, and include existing extension applications and authority decisions. These records allow an assessment of whether timely delivery remains achievable, which authority decision is missing, and what obstacles remain to safe seasonal operation.

FAQ

Questions about periodic cableway inspections

Does commissioning an inspection body preserve the deadline? +
Under § 3 Abs. 6 SeilbÜV 2013, compliance depends on the date the report reaches the operator. Neither commissioning the inspection nor agreeing on an inspection date replaces that delivery.
Does a late inspection start a new five-year cycle? +
The six-month tolerance and limited extension leave the next inspection deadline unchanged. Under § 3 Abs. 5, a reasoned application is required to change the starting date, and such a change must not cause any inspection deadline to be exceeded.
Does the further six-month period apply automatically? +
You must apply to the authority for the additional extension and explain the reasons. This extension is limited to a maximum of a further six months. You must submit the application no later than four weeks before the first six-month period ends, and filing alone does not mean an extension has been granted.

Had an accident?

The sooner we secure the evidence, the better we can enforce your claim. Call us directly or send an email, callback within one business day.

Contact

A direct line to the firm.

Address

BRANDAUER Rechtsanwälte GmbH Giselakai 51 5020 Salzburg